Delivering essential cost control, reporting, measurement services, and commercial guidance throughout the project's duration, Senate's focus was on ensuring optimal value for money was attained specifically for the fire remediation works.

Scroll Down
Budget

£5.7 million

Description

Senate was appointed as the Commercial Manager on behalf of their client, undertaking duties that covered Sub-Contract administration, full quantity surveying, and comprehensive commercial management. Working in close liaison with the Employer’s Agent and the Main Contractor, our involvement spanned the entire project lifecycle. Initially, this included tendering processes, contract negotiations, and contract award. Subsequently, our post-contract work involved valuing progress, assessing variations and changes (incorporating re-measurements), performing cost reporting, and finalising the project account.

Challenge

To replace the existing curtain wall with a new system, whilst the ground floor showroom and the offices remained occupied.

Goal

Document and assure, through robust QAQC processes, a fully compliant replacement curtain wall system.

Outcome

The project, a particularly tricky undertaking where the original scope grew exponentially due to issues uncovered, concluded with a successfully agreed Final Account. The project was completed on time, with the client and contract administrator being entirely satisfied, such that repeat business is underway.